New England House – ‘High level’ timetable

 

Task

Timetable

Develop Design/Planning application

Jan – Jul 2021

Submit Planning Application

Jul - Dec 2021

Planning Determination Period

Dec 2021 – Mar 2022

Planning Conditions

Jul 2021 – Mar 2022

Technical Design Period (RIBA Stage 4)

Jul 2021 – Mar 2022

Measurement and Pricing

Apr 2022 – Jul 2022

Mobilisation and Tender Evaluation

Aug 2022 – Dec 2022

Start on site

Jan 2023

Build Period (18 months)

Feb 2023 to Jul 2024